Month: October 2020

Month: October 2020

Gratomic Announces Aukam Graphite Property Construction Update

The Gratomic team has completed the excavations intended to contain the concrete foundations that will accommodate the custom designed processing equipment including material thickener, cyclone, material hopper, settling reservoir, and filter press. Gratomic is currently preparing to begin pouring concrete in these areas the second week of October. The current pilot sump area will be designated to house the new floatation columns and mixing tanks. The filter press area has been prepared and excavation is currently scheduled to begin October 6th on the product dryer area. Final general assembly and layout of the Aukam processing plant have been completed. On site Management has received the cement from Pupkewitz Megabuild – Keetmanshoop. Aggregate and bricks were received from Dolerite Brick & Sand